Fonds GB 0096 MS1122 - London and Birmingham Railway

Identity area

Reference code

GB 0096 MS1122

Title

London and Birmingham Railway

Date(s)

  • -23343 (Creation)

Level of description

Fonds

Extent and medium

1 item

Context area

Name of creator

Biographical history

The London and Birmingham Railway was sanctioned in 1833, and the Company appointed Robert Stephenson as chief engineer. Its construction was dogged by much opposition. The 112 mile long London to Birmingham line took 20,000 men nearly five years to build. The total cost of building the railway was £5,500,000 (£50,000 a mile). The railway was opened in stages and finally completed on 17 September 1838. The line started at Birmingham's Curzon Street Station and finished at Euston Station in London.

Archival history

GB 0096 MS1122 1836 February Fonds 1 item London and Birmingham Railway

The London and Birmingham Railway was sanctioned in 1833, and the Company appointed Robert Stephenson as chief engineer. Its construction was dogged by much opposition. The 112 mile long London to Birmingham line took 20,000 men nearly five years to build. The total cost of building the railway was £5,500,000 (£50,000 a mile). The railway was opened in stages and finally completed on 17 September 1838. The line started at Birmingham's Curzon Street Station and finished at Euston Station in London.

Senate House Library

Drawing of Tring cutting in Hertfordshire, 1836, which was built as part of the London and Birmingham Railway.

1 item only

Open for research

This item may be copied subject to an inspection of its physical condition
English

Fonds description only

Senate House Library holds other archives, which relate to the London and Birmingham Railway (Refs: MS504, MS940). The Goldsmiths collection at Senate House Library also includes plans for the "Tring" line, circa 1840 (Ref: [G.L.] Case II.7 [Railways Portfolio]).

The National Archives, London, holds business records, 1830-1849 and 1833-1877 (Ref: RAIL 384); Salford University Library contains miscellaneous correspondence from directors, 1830; Bristol University Library holds minutes of evidence given before the House of Lords Committee, 1832 (Ref: DM 1528); the National Railway Museum Library and Archive contains drawings of Curzon Street Station, Birmingham, [1838-1840].

Tring cutting was the largest of its kind in the early railway era with a length of two and half miles and a depth of 40 feet. A big problem for the engineers of the London and Birmingham Railway was building through the chalk ridge of the Chilterns. The solution was to cut through the bottom of the Bulbourne valley. The cutting was built using "horse runs". Horses at the top of the cutting were harnessed to big barrows by lengths of rope over a pulley. The barrow, when filled with earth, was pulled up a steep plank-way by horses, with navvies in attendance. Any irregular movement of the horse could propel both man and barrow into the cutting. There were some 40 of these horse runs used in the construction work at Tring.
Entry compiled by Richard Temple.

Compiled in compliance with General International Standard Archival Description, ISAD(G), second edition, 2000; National Council on Archives Rules for the Construction of Personal Place and Corporate Names 1997.

2006-09-16, Richard Temple Construction industry England Europe Hertfordshire Industry Railway construction Tring UK Western Europe London

Immediate source of acquisition or transfer

Senate House Library

Content and structure area

Scope and content

Drawing of Tring cutting in Hertfordshire, 1836, which was built as part of the London and Birmingham Railway.

Appraisal, destruction and scheduling

Accruals

System of arrangement

1 item only

Conditions of access and use area

Conditions governing access

Open for research

Conditions governing reproduction

This item may be copied subject to an inspection of its physical condition

Language of material

  • English

Script of material

  • Latin

Language and script notes

English

Physical characteristics and technical requirements

Senate House Library holds other archives, which relate to the London and Birmingham Railway (Refs: MS504, MS940). The Goldsmiths collection at Senate House Library also includes plans for the "Tring" line, circa 1840 (Ref: [G.L.] Case II.7 [Railways Portfolio]).

Finding aids

Fonds description only

Allied materials area

Existence and location of originals

Existence and location of copies

Related units of description

The National Archives, London, holds business records, 1830-1849 and 1833-1877 (Ref: RAIL 384); Salford University Library contains miscellaneous correspondence from directors, 1830; Bristol University Library holds minutes of evidence given before the House of Lords Committee, 1832 (Ref: DM 1528); the National Railway Museum Library and Archive contains drawings of Curzon Street Station, Birmingham, [1838-1840].

Related descriptions

Publication note

Tring cutting was the largest of its kind in the early railway era with a length of two and half miles and a depth of 40 feet. A big problem for the engineers of the London and Birmingham Railway was building through the chalk ridge of the Chilterns. The solution was to cut through the bottom of the Bulbourne valley. The cutting was built using "horse runs". Horses at the top of the cutting were harnessed to big barrows by lengths of rope over a pulley. The barrow, when filled with earth, was pulled up a steep plank-way by horses, with navvies in attendance. Any irregular movement of the horse could propel both man and barrow into the cutting. There were some 40 of these horse runs used in the construction work at Tring.

Notes area

Note

Tring cutting was the largest of its kind in the early railway era with a length of two and half miles and a depth of 40 feet. A big problem for the engineers of the London and Birmingham Railway was building through the chalk ridge of the Chilterns. The solution was to cut through the bottom of the Bulbourne valley. The cutting was built using "horse runs". Horses at the top of the cutting were harnessed to big barrows by lengths of rope over a pulley. The barrow, when filled with earth, was pulled up a steep plank-way by horses, with navvies in attendance. Any irregular movement of the horse could propel both man and barrow into the cutting. There were some 40 of these horse runs used in the construction work at Tring.

Alternative identifier(s)

Access points

Subject access points

Place access points

Name access points

Genre access points

Description control area

Description identifier

Institution identifier

Senate House Library, University of London

Rules and/or conventions used

Compiled in compliance with General International Standard Archival Description, ISAD(G), second edition, 2000; National Council on Archives Rules for the Construction of Personal Place and Corporate Names 1997.

Status

Level of detail

Dates of creation revision deletion

Language(s)

  • English

Script(s)

    Sources

    Accession area