London and Birmingham Railway
forme(s) parallèle(s) du nom
Forme(s) du nom normalisée(s) selon d'autres conventions
Autre(s) forme(s) du nom
Numéro d'immatriculation des collectivités
Zone de description
Dates d’existence
Historique
The London and Birmingham Railway was sanctioned in 1833, and the Company appointed Robert Stephenson as chief engineer. Its construction was dogged by much opposition. The 112 mile long London to Birmingham line took 20,000 men nearly five years to build. The total cost of building the railway was £5,500,000 (£50,000 a mile). The railway was opened in stages and finally completed on 17 September 1838. The line started at Birmingham's Curzon Street Station and finished at Euston Station in London.